SUMMER CONSTRUCTION   

October 15, 2019: Post Office Alley is complete with the exception of landscaping to be installed by the end of the month. Varsity Alley's new lighting is being installed and old lights removed this week. Some additional brickwork is also planned near the rear archway.

August 26, 2019: Post Office Alley is nearly complete with the only element left to install being the archway on the Wallace Deck end of the Alleyway. Varsity Alley work is underway with the stone steps adjacent to the alleyway in the Rosemary Columbia Parking lot.

All businesses in the area are accessible. Pedestrians are diverted from the Wallace Deck to Rosemary and Henderson streets to access Franklin Street. Both Alleys will be accessible during UNC football games.

June 10, 2019:  Post Office and Varsity Alleys are under construction. The project includes new railings, lighting, wayfinding signage and drainage at Varsity Alley, 119 E. Franklin St.; and Post Office Alley, 179 E. Franklin St. Each alley will feature new entry arches. Another nearby walkthrough, Amber Alley, was updated in December 2017 with new lighting, signage and public art.

For more information, contact Director of Organizational and Strategic Initiatives Rae Buckley at rbuckley@townofchapelhill.org

Project Overview 

A key project in the Downtown 2020 Work Plan is to improve Access and Variety in the Downtown. Our project goal is to design improvements for downtown pedestrian alleyways that will address safety concerns, provide opportunities for place-making and expand wayfinding accommodations using both traditional and experimental techniques. Improvements include:

  • Amber Alley improved lighting, electrical trenching, concrete repairs and temporary signage
  • Post Office Alley: renovations will include repaving the sidewalk; lowering planters to increase safety; installing wayfinding arch at the rear of the alley; and replacing the railing at the rear of the alley with a new, matching railing.
  • Varsity Alley renovations include increased lighting; installing two arches (one at each end of the alley); repairing stairs.
  • North Alley clean up and other improvements

Post Office and Varsity Alleys

The Town is working with local landscape architecture firm Swanson & Associates to design the above described improvements to the Post Office and Varsity Alleys. The objectives are to increase safety through lighting and lowering planters; adding wayfinding elements (arches) to identify the alleys and make them more welcoming to pedestrians; and making a beautiful blank canvas for future art installations.

These plans are based on the early 2017 public input process described below. Construction will begin in May 2019.

Click here for final construction plans from October, 2018 for Post Office and Varsity Alleys

Click here for the report of design opportunities for the Post Office and Varsity Alley from March, 2017.

 

Amber Alley

Amber Alley has new lighting, trenching and signage completed in December, 2017. The trenching connected new lighting in the alley to Town-supplied power from the Wallace Deck and the signage directs pedestrians from the Wallace Deck to Franklin Street and back through Amber Alley. Concrete repairs were also performed to fix cracked areas in the North Alley.

The signage and lighting improvement are part of the Town's continuing efforts to experiment with new ways of adding wayfinding, vibrancy, lighting and amenities to the Downtown. The Town welcomes your input which can be sent to info@townofchapelhill.org.

171229_Alley_Repairs_01  171212_Amber_Alley_05

Trenching was completed and art signs installed in December, 2017. The art signs were created by local Garner artist Frank Kreacic and come alive when viewed with 3D glasses.

North Alley

North Alley refers to the driveway around the Wallace Parking Deck on E. Rosemary St. This space is often the first impression visitors to Downtown and UNC receive and, as such, is of importance to the Town and Downtown stakeholders. A cross-agency team of Town and County employees from many departments has been examining opportunities to improve this space and the Town is partnering with private property owners to improve space that borders Town and private property.

Improvement opportunities and related projects include:

  • Aesthetic and functional improvements to the Wallace Deck Bathrooms
  • Re-striping and removing grease containers on Town property around County recycling dumpsters
  • Improved oversight of garbage, recycling, and grease containers
  • Connections between Amber Alley and Post Office Alley renovations, described above
  • Wallace Parking Deck expansion and how it will affect the alleyway
North Alley BEFORE   North Alley AFTER 1

Before and After Chapel Hill Police Department improved area behind Wallace Parking Deck along North Alley.

Public Meetings

Public input meetings were held in the fall of 2016 and early winter 2017. Residents were invited to provide feedback on different design ideas. This input is being incorporated into the design drawings.

Alleyway    

Post Office and Amber Alleys as they exist today.

This project is sponsored by the Town and is supported by the professional firm of Swanson + Associates, P.A. For more information, contact Sarah Poulton (spoulton@townofchapelhill.org or 919-969-5009) or David Swanson (david@swansonlandscapearchitecture.com).

 

Redball 2 9-23-18Redball 1 9-23-18

The Redball Project came to Varsity Alley in September, 2018.