Streets scheduled to be resurfaced in 2017

The Town of Chapel Hill’s annual resurfacing program will begin in July 2017. The purpose of this project is to preserve and enhance the physical and operating conditions of the Town’s roadway system.

The proposed work will include utility adjustments and may include patching, grinding of the asphalt, pedestrian curb cut improvements and replacement of badly deteriorated curb and gutter prior to resurfacing.

During construction we will work to minimize inconveniences, though some parking and access to driveways may be temporarily blocked and motorists should anticipate some minor delays during the work week. We apologize for any inconvenience and appreciate your patience and cooperation during the period of improvement.

The project is expected to be completed by October 20, 2017. Equipment failures or weather conditions could extend the time. For more information, contact Greg Ling at 919-969-5165.

Below are streets scheduled for resurfacing.

.

STREET

FROM

TO

Meadowmont Lane

Highway 54

Sprunt Street

Barbee Chapel Road

Highway 54

Highway 54

Curtis Road

Clayton Road

S. Lakeshore Drive

Rosemary Street

Henderson Street

Hillsborough Street

Henderson Street

Cobb Terrace

Franklin Street

 

Below are streets scheduled for reconstruction. Street reconstruction involves removal of the existing asphalt surface and sub-base of the road and rebuilding the road from the bottom up.

STREET

FROM

TO

Friday Center Drive**

Hwy 54

Median

 

**Friday Center Drive reconstruction is tentatively scheduled to begin in Fall 2017 or Spring 2018.

 